2. Explain an impossible request¶
A customer now asks for job C to finish by time six. The base workshop model is feasible, but this extra request conflicts with the dependency chain A → B → C, whose durations sum to seven.
Start with the shared scheduling model. Enable unsat-core production before checking, as the complete program does during setup.
Isolate the new requirement¶
Use a pushed scope for the rush request. Its constraint concerns only C;
it does not impose a deadline on every job. An unsat result means this
request cannot be satisfied alongside the base requirements.
solver.push()
var rush = tm.mkTerm(Kind.LEQ, ends[2], tm.mkInteger(6))
solver.assertFormula(rush)
var conflict = solver.checkSat()
assert_true(conflict.isUnsat())
var core = solver.getUnsatCore()
var core_labels = List[String]()
var includes_rush = False
for term in core:
if term == rush:
core_labels.append("C must finish by 6")
includes_rush = True
else:
var matched = False
for i in range(len(requirements)):
if term == requirements[i]:
core_labels.append(labels[i])
matched = True
break
assert_true(matched)
assert_true(includes_rush)
assert_equal(len(core_labels), len(core))
print("rush deadline:", conflict)
print("core labels recognized:", len(core_labels) == len(core))
solver.pop()
The returned core contains asserted terms. The program maps each one to a
label by comparing it with the original requirement terms. Here Mojo
term == requirement compares the symbolic expressions; it does not build
a new SMT equality. Logical equality inside a constraint instead uses
mkTerm(Kind.EQUAL, ...).
The special rush constraint gets its own label, “C must finish by 6.” The other labels come from the same list that was assembled with the model. Keeping a source formula with its label avoids trying to diagnose the problem by parsing printed SMT syntax.
Interpret the explanation carefully¶
The core is an inconsistent subset of the assertions. It is not necessarily the smallest inconsistent subset, nor a unique explanation. Its order and choice of redundant requirements need not remain stable. That is why the program checks that every core term has a recognized label, without recording one particular core ordering as expected output.
The rush request must appear in a valid core here: the base model was
already shown satisfiable. The program checks this property explicitly.
The final pop removes the request, allowing the same solver to proceed
to deadline search.
An interface can present the labels as conflicting requirements and let a person revise one. Choosing which requirement to relax is an application decision. A core by itself does not rank the cost or importance of a change.
Exercise: explain the mathematical conflict¶
Why is the six-unit deadline impossible even if the second machine were unlimited?
Worked answer. A cannot start before zero. B cannot start until A's two units finish, and C cannot start until B's three units finish. C then needs two units itself. These dependencies force C's end to be at least seven, independently of the capacity constraints and job D.