3. Find and certify the minimum deadline¶
A feasible schedule answers “can we finish by this time?” To find the minimum deadline, solve a sequence of feasibility problems and retain certified bounds. This application uses ordinary solver queries rather than requiring an optimization-specific API.
Prerequisite: the shared model and its deadline helper.
Use monotonicity¶
If all jobs can finish by integer deadline d, the same schedule meets
any larger deadline. If deadline d is impossible, every smaller deadline
is impossible. This follows from the direction of the inequalities
end_i <= d; the other requirements do not change during search.
Maintain two bounds: low is proved infeasible and high is proved
feasible. The program establishes both before entering the loop. A midpoint
query then replaces the corresponding bound, preserving the invariant:
# Maintain: low is infeasible and high is feasible.
var low = 0
var high = 10
assert_true(check_deadline(solver, tm, ends, requirements, low).isUnsat())
assert_true(check_deadline(solver, tm, ends, requirements, high).isSat())
while high - low > 1:
var middle = low + (high - low) // 2
var candidate = check_deadline(solver, tm, ends, requirements, middle)
if candidate.isSat():
high = middle
elif candidate.isUnsat():
low = middle
else:
raise Error("deadline search inconclusive; keep the last certified bounds")
assert_equal(high, 7)
assert_true(check_deadline(solver, tm, ends, requirements, high).isSat())
assert_true(check_deadline(solver, tm, ends, requirements, high - 1).isUnsat())
print("minimum integer deadline:", high)
print("adjacent smaller deadline: unsat")
When high - low == 1, there is no integer deadline between the bounds.
Thus high is the smallest feasible integer deadline. The final two
queries explicitly check the claimed optimum and the adjacent smaller
bound, which also makes the conclusion easy to review independently.
Preserve inconclusive outcomes¶
Only sat moves the upper bound and only unsat moves the lower bound.
An unknown result leaves both unchanged. This demonstration raises an
error instead of printing an unproved optimum. An interactive application
could report the last certified bracket and let its caller retry with a
larger budget or a different search strategy.
Likewise, the initial feasible upper bound must be established before search starts. In a larger application, finding that bound may require expanding the candidate deadline. If the whole model is infeasible, no amount of deadline expansion repairs it; separate structural conflicts from an overly tight objective.
Check the answer independently¶
The dependency chain A → B → C gives a lower bound of 2 + 3 + 2 = 7.
The schedule shown in the first chapter
finishes by seven. A lower bound and an attaining schedule establish the
same optimum as the solver queries.
The integer time model matters. Searching adjacent integers proves an optimum on that grid. For continuous start times or a continuous objective, one-unit adjacency does not rule out an intermediate improvement. You would need an exact optimality argument or a stated tolerance and a certified remaining interval.
Exercise: use a different search strategy¶
Would testing deadlines in descending order from ten still establish the same optimum?
Worked answer. Yes, if each required query is decided and the process
stops only after the first infeasible smaller deadline. Binary search uses
fewer feasibility checks when the initial integer bracket is wide, but
neither strategy may treat unknown as infeasible.