Scheduling application

3. Find and certify the minimum deadline

A feasible schedule answers “can we finish by this time?” To find the minimum deadline, solve a sequence of feasibility problems and retain certified bounds. This application uses ordinary solver queries rather than requiring an optimization-specific API.

Prerequisite: the shared model and its deadline helper.

Use monotonicity

If all jobs can finish by integer deadline d, the same schedule meets any larger deadline. If deadline d is impossible, every smaller deadline is impossible. This follows from the direction of the inequalities end_i <= d; the other requirements do not change during search.

Maintain two bounds: low is proved infeasible and high is proved feasible. The program establishes both before entering the loop. A midpoint query then replaces the corresponding bound, preserving the invariant:

schedule_application.mojo Download
# Maintain: low is infeasible and high is feasible.
var low = 0
var high = 10
assert_true(check_deadline(solver, tm, ends, requirements, low).isUnsat())
assert_true(check_deadline(solver, tm, ends, requirements, high).isSat())
while high - low > 1:
    var middle = low + (high - low) // 2
    var candidate = check_deadline(solver, tm, ends, requirements, middle)
    if candidate.isSat():
        high = middle
    elif candidate.isUnsat():
        low = middle
    else:
        raise Error("deadline search inconclusive; keep the last certified bounds")
assert_equal(high, 7)
assert_true(check_deadline(solver, tm, ends, requirements, high).isSat())
assert_true(check_deadline(solver, tm, ends, requirements, high - 1).isUnsat())
print("minimum integer deadline:", high)
print("adjacent smaller deadline: unsat")

When high - low == 1, there is no integer deadline between the bounds. Thus high is the smallest feasible integer deadline. The final two queries explicitly check the claimed optimum and the adjacent smaller bound, which also makes the conclusion easy to review independently.

Preserve inconclusive outcomes

Only sat moves the upper bound and only unsat moves the lower bound. An unknown result leaves both unchanged. This demonstration raises an error instead of printing an unproved optimum. An interactive application could report the last certified bracket and let its caller retry with a larger budget or a different search strategy.

Likewise, the initial feasible upper bound must be established before search starts. In a larger application, finding that bound may require expanding the candidate deadline. If the whole model is infeasible, no amount of deadline expansion repairs it; separate structural conflicts from an overly tight objective.

Check the answer independently

The dependency chain A → B → C gives a lower bound of 2 + 3 + 2 = 7. The schedule shown in the first chapter finishes by seven. A lower bound and an attaining schedule establish the same optimum as the solver queries.

The integer time model matters. Searching adjacent integers proves an optimum on that grid. For continuous start times or a continuous objective, one-unit adjacency does not rule out an intermediate improvement. You would need an exact optimality argument or a stated tolerance and a certified remaining interval.

Exercise: use a different search strategy

Would testing deadlines in descending order from ten still establish the same optimum?

Worked answer. Yes, if each required query is decided and the process stops only after the first infeasible smaller deadline. Binary search uses fewer feasibility checks when the initial integer bracket is wide, but neither strategy may treat unknown as infeasible.

Continue with the task cookbook or return to the learning path.